Uncertainty over the new Greece-Italy cable: Italian energy regulator calls for a review of timeline and costs

Arera calls for priority to be given to the northern border, while expressing strong reservations about the extension to the southern lines with Greece and Tunisia

Newsroom August 12 03:22

Δείτε περισσότερα άρθρα μας στα αποτελέσματα αναζήτησης

Add Protothema.gr on Google

As Athens and Rome push for the creation of a new electrical “corridor” between Greece and Italy, Italy’s energy regulator Arera is sending a clear message that the immediate priority is the country’s northern interconnections.

In a recent submission to the operator of the Italian transmission system Terna, Arera called for priority to be given to the projects deemed most cost-effective, namely the expansion of interconnection capacity to the north by at least 2.6 GW. For the southern lines – with Greece and Tunisia – the authority expresses significant reservations, especially regarding the time horizon of the benefits for Italy.

>Related articles

Balcony solar panels: New framework for self-consumption, batteries & cheaper electricity

Cyprus condemns the illegal memorandum of understanding between Turkey and the occupied territories regarding the construction of a natural gas pipeline

Vertical Corridor: Interest in natural gas exports to six countries in Southeast Europe

Positions on the timetable

The new Greece-Italy interconnection, with a capacity of 1,000 MW, is planned to be completed between 2033 and 2035. However, according to Arera, “substantial benefits” for Italy are expected only after 2040, leading the authority to recommend a review of the timetable.

The issue of costing is also on the table, as Arera is asking for additional analysis. In the documents submitted by Terna for the selection process of this year’s PCI/PMI projects, the estimate reaches 1.9 billion euros, while in the 10-year programs of ADMIE and ENTSO-E the corresponding amount is 1.25 billion euros.

The figure of 1.1 billion euros is 1.1 billion euros.

Ask me anything

Explore related questions

#energy#Greece-Italy cable
> More Economy

Follow en.protothema.gr on Google News and be the first to know all the news

See all the latest News from Greece and the World, the moment they happen, at en.protothema.gr

> Latest Stories

Syros paramedic dies after stabbing at couple’s home

July 23, 2026

Newly opened E65 motorway answers where Recovery Fund money went, says Prime Minister

July 23, 2026

Trump warns he’s considering a “massive attack” on Iran, bigger than any before

July 23, 2026

Confessed killer of Stavros Georgiou taken before prosecutor

July 23, 2026

Prime Minister: New e-scooter rules put prevention and child safety first

July 23, 2026

Irish widow marks eight years since Mati wildfire tragedy that killed her husband days after their wedding

July 23, 2026

Hatzivasileiou in Vilnius: Preparations for Greece’s EU Presidency take centre stage

July 23, 2026

Venezuela earthquakes caused $19.6 billion in damage, World Bank says

July 23, 2026
All News

> Greece

In reverence, the emotional deposition in Jerusalem, see photos & video

The Holy Temple of the Resurrection opened after many days due to the war between Israel and Iran

April 10, 2026

In the final stretch for the accreditation of joint master’s degrees: Aiming for their launch in the coming academic year

April 10, 2026

Schedule for Epitaph Procession today (10/4)

April 10, 2026

Perfect weather for Easter excursions, according to Tsatrafyllia’s forecast

April 10, 2026

Easter in Greece: The customs that continue in Greek tradition – From Nafpaktos to Corfu

April 10, 2026
Homepage
PERSONAL DATA PROTECTION POLICY COOKIES POLICY TERM OF USE
Powered by Cloudevo
Copyright © 2026 Πρώτο Θέμα